* Completion was planned for 2020
* Delay could be a few years
* Supervisory board member says delay in supplier tender
* Potental suppliers had asked for delay
By Jana Mlcochova and Jan Korselt
(Adds analyst comment, background, recasts)
PRAGUE, Oct 13 (Reuters) - Czech power group CEZ <
> will delay the planned construction of new units at its Temelin nuclear power plant amid forecasts for declining electricity demand in coming years, CEZ officials said on Wednesday.The utility, also the region's biggest listed company, plans to build two additional units at its Temelin plant near Austria as well as up to three other units in neighbouring Slovakia and at its Dukovany station in the Czech Republic.
CEZ -- central Europe's biggest utility -- was expected this autumn to ask bidders to submit final offers for the construction and announce the winner of the tender by the end of the next year. The completion date was set for 2020.
Some analysts said tight cash flow could be a reason for the delay and predicted CEZ may seek a partner for the project that could be worth up to 500 billion Czech crowns ($28.3 billion).
"Nuclear power plants are the cheapest source of energy for CEZ," Prague-based brokerage Atlantik said in a research note. "In addition, no emission credits are needed.
"The report of a possible delay is not a good one for investors and we expect a negative market reaction."
CEZ shares were off nearly 1 percent to 808 crowns in late morning trading. The Prague bourse's PX Index <
> was up nearly 1 percent.Czech officials, who said the suppliers had asked for a delay to better prepare their bids, have painted the Temelin expansion as something that would help secure the country's energy security and cement its place as one of Europe's top electricity exporters.
Local newspaper Hospodarske Noviny quoted an unnamed CEZ source as saying the delay could be "in the order of years" and that the utility might sell some assets abroad.
CEZ officials confirmed the delay but declined to give more details.
CEZ supervisory board member Eduard Janota told Reuters in a telephone interview there was a delay in the tender for a supplier of the new units but he declined to give more details, saying the issue would be debated at a CEZ supervisory board meeting on Thursday.
"There is already a delay now, because the tender should have originally happened in autumn and it will not happen, it will take place in the soonest possible term, which is in spring," he said.
Toshiba Corp <6502.T> unit Westinghouse, an alliance of Russia's Atomstroyexport and Czech company Skoda JS, and France's Areva <CEPFi.PA>, are bidding to build the units.
CEZ spokesman Ladislav Kriz said it has not been decided yet whether the entire expansion plan at Temelin would be delayed.
He said CEZ was in talks about the timetable with all the three suppliers, who he said had sought a longer period to complete bids and for timing of deliveries for the construction.
"Things will be clear within 14 days, one month," Kriz said.
(Writing by Jana Mlcochova and Michael Kahn, editing by Keiron Henderson)